Project Name: Centrifuge & Filter Press Buildings
Project Overview: Supply, fabrication and installation of two hot-dip galvanised steel process buildings on an expedited timeline.
Project Location: Central West NSW
Type of Shed/Solution: Process Plant Buildings
Industry: Water Treatment & Energy
Project Overview
A new water treatment plant at a power station site in NSW needed dedicated buildings to house its sludge dewatering equipment: a filter press building and a centrifuge building. Asset Building Systems was engaged by the head contractor to supply, fabricate and install both structures.
We had already delivered other buildings on the same plant for this client. When the programme tightened, the client asked us to revise our offer to bring the timeline forward, and we were able to restructure our approach so both buildings could go up faster.
Project Scope and Objectives
The priority was speed without any compromise on quality. The filter press building was needed first, followed by the centrifuge building. Scope for each building included:
- Shop drawings of all steelwork
- Fabrication of hot-dip galvanised structural steel members
- Supply and installation of the steel-framed building
- Support frames for plant equipment in the filter press building
- Stairs, handrails and Australian-fabricated grating at plant level
- Colorbond Ultra roof cladding with sarking, and cladding to the upper-level walls
- Gutters, downpipes and an industrial-grade personnel door
- Weld inspection and full quality assurance documentation
Fast-Tracking the Programme
To bring the timeline forward we built a revised programme targeting the filter press building’s structure being erected before the Christmas shutdown, with the centrifuge building following straight after. This relied on:
- Fast turnaround and sign-off of shop drawings
- Swapping the specified imported grating, which had a six-week lead time, for an Australian-fabricated alternative
- Close coordination with the client on crane availability, equipment bracket dimensions and access
- The same experienced crew who had already built other structures on the plant
Onsite Installation Process
Steel was fabricated and galvanised off site, then delivered and erected in sequence. Every stage was covered by an inspection and test plan, and welds were visually scanned and inspected, with sign-off records kept for each member. Galvanised steel was specified throughout the primary structure to give long-term corrosion resistance in a wet process environment.
Project Challenges and Solutions
Misaligned hold-down bolts:
During construction we found that the footing hold-down bolts installed by an earlier contractor were out of alignment. Rather than delay the programme while footings were reworked, our team worked with the client’s engineers to design custom base plate adapters. These heavy fabricated plates bridged the gap between the bolts as installed and the column positions, backed by a dedicated weld inspection process.
Late equipment changes:
When the client needed the grating and supports modified to suit a second centrifuge, we turned the changes around quickly to keep the building aligned with the process equipment.
Client Collaboration and Adaptability
Working as part of a larger delivery team on a critical infrastructure project meant fitting in with the head contractor’s programme, crane bookings and site rules. We kept communication open with the client’s engineers so problems like the bolt alignment were solved quickly and the programme kept moving.
Completion and Outcomes
Both buildings were delivered on time and to specification, giving the client:
- Purpose-built, galvanised steel housings for its dewatering equipment
- Safe access to plant via stairs, handrails and grating
- A fully documented quality record for handover
- A practical fix for an inherited footing problem, with no programme delay
Benefits Secured
- An expedited programme built around the Christmas shutdown
- Lead time removed by using Australian-fabricated grating
- Engineered solutions to site issues, without rework of footings
- Continuity of an experienced crew across multiple buildings on the plant
Final Thoughts
Water treatment and energy projects leave little room for delay. This project shows how Asset Building Systems adapts its approach to meet tight programmes on critical infrastructure, while keeping quality and compliance front and centre.
Planning a similar project? See our water and wastewater infrastructure buildings page for how we design and build them across NSW, or talk to our team.